Current status |
DPR approved by KIIFB on 07.02.2020 for an amount of Rs.36.12 Cr. Project was pending due to Semi High Speed Rail project of KRDCL. Railways directed to submit revised GAD for all ROBs long pending due to Silver line vide letter dated 14.03.2023.
LUS inspection conducted on 04.07.2023 and report received. Revised GAD submitted on 25.09.2023. GAD scrutiny in progress with Railway.
In the meeting conducted with the Kozhikode District Collector on 24.05.2025, it was decided to construct the Nelliyady ROB and provide a connection to Muchukunnu via a service road. |