Projects

Chungam Gate ROB

Back

General Details
Administrative Sanction Order Number Dated Amount(crores)
GO(Rt)No.718/2018/PWD 19.04.2018 22.51
District Kozhikode
LAC Kozhikode North
Location
Project Details
Actual Start Date 19.04.2018
Project Management Consultant ISA
Category Road Over Bridges
LC No 190
Railway (km) 670/000-100
Length Including Approaches 468 m
Width of ROB 10.2 m
GAD Status Not Approved
No of Lanes 2
Financial Details
AS Amount(crores) 22.51
Funded By KIIFB
Project Outlay(crores) 37.83
Work Progress Details
Physical progress 75 %
Current status DPR approved by KIIFB on 07.02.2020 for an amount of Rs.37.83 Cr. Project was pending due to Semi High Speed Rail project of KRDCL. Railways directed to submit revised GAD for all ROBs long pending due to Silver line vide letter dated 14.03.2023. Revised GAD submitted on 18.08.2023. Returned for correction on 18.10.2023. Revised GAD submitted on 27.02.2024. In the meeting conducted with the Kozhikode District Collector on 24.05.2025, it was decided to construct the Chungam Gate ROB and provide connection to Temple Gate via a service road.