General Details | |||
---|---|---|---|
Administrative Sanction | Order Number | Dated | Amount(crores) |
GO(Rt)No.718/2018/PWD | 19.04.2018 | 22.51 | |
District | Kasargod | ||
LAC | Thrikaripur | ||
Location |
Project Details | |
---|---|
Actual Start Date | 19.04.2018 |
Project Management Consultant | ISA |
Category | Road Over Bridges |
LC No | 267 |
Railway (km) | 795/500-600 |
Length Including Approaches | 521 m |
Width of ROB | 10.2 m |
GAD Status | Not Approved |
No of Lanes | 2 |
Financial Details | |
---|---|
AS Amount(crores) | 22.51 |
Funded By | KIIFB |
Project Outlay(crores) | 32.24 |
Work Progress Details | |||
---|---|---|---|
Physical progress | 75 % | ||
Current status | DPR approved by KIIFB on 10.02.2020 for an amount of Rs.32.24 Cr. GAD approved on 28.11.2024. Land acquisition Requisition will be submitted within one month. LA plan under preparation. |