| General Details | |||
|---|---|---|---|
| Administrative Sanction | Order Number | Dated | Amount(crores) |
| GO(Rt)No.718/2018/PWD | 19.04.2018 | 22.51 | |
| District | Thrissur | ||
| LAC | Puthukkad | ||
| Location | |||
| Project Details | |
|---|---|
| Actual Start Date | 19.04.2018 |
| Project Management Consultant | ISA |
| Category | Road Over Bridges |
| LC No | 33 |
| Railway (km) | 51/600-700 |
| Length Including Approaches | 335.44 |
| Width of ROB | 10.20 |
| GAD Status | Not approved |
| No of Lanes | 2 |
| Financial Details | |
|---|---|
| AS Amount(crores) | 22.51 |
| Funded By | KIIFB |
| Project Outlay(crores) | 21.87 |
| Work Progress Details | |||
|---|---|---|---|
| Physical progress | 75 % | ||
| Current status | Final GAD & alignment plan submitted to Railways on 17.02.2022. Vide letter dated 11.07.2022, Railway informed that GAD of ROB’s between Ernakulam and Shornur will be approved only after finalization of 3rd line. Alignment of 3rd and 4th line received from Railway. GAD submitted to railways on 01.01.2026. Maintenance Agreement Shared on 20.05.2026. Awaiting approval of GAD from Railways. | ||