Current status |
DPR approved on 06.08.2020 for an amount of Rs. 33.19Cr. A
On 11.07.2022, Railway had given in-principle approval for starting the land acquisition. On 21.03.2023, Railway informed that this ROB proposal is falling on the alignment of proposed 3rd & 4th Line between Coimbatore and Shornur and hence the GAD is kept on hold. On 19.07.2024 Railways requested to revise the GAD. Revised GAD submitted to Railway on 05.10.2024. Revised GAD again submitted to Railway on 04.03.2025 incorporating comments from Railways.
LA requisition submitted to District Collector on 29.10.2022. 4(1) published on 26.07.2024 and SIA study completed. Expert committee meeting completed and report submitted to District Collector. Awaiting 11(1) notification. |