Current status |
DPR approved on 06.08.2020 for an amount of Rs. 33.19Cr. After several revisions, final GAD submitted to Railways on 31.08.2021. Reminder letter send on 30.06.2022.
On 11.07.2022, Railway had given in-principle approval for starting the land acquisition. LA requisition submitted to District Collector on 29.10.2022. LAO was appointed. Boundary stone planting completed & Joint inspection conducted on 08.02.2023. On 21.03.2023, Railway informed that this ROB proposal is falling on the alignment of proposed 3rd & 4th Line between Coimbatore and Shoranur and hence the GAD is kept on hold. On 19.07.2024 Railways requested to revise the GAD. Revised GAD is under preparation. |