| General Details | |||
|---|---|---|---|
| Administrative Sanction | Order Number | Dated | Amount(crores) |
| GO(Rt)No.718/2018/PWD | 19.04.2018 | 22.51 | |
| District | Palakkad | ||
| LAC | Malampuzha | ||
| Location | |||
| Project Details | |
|---|---|
| Category | Road Over Bridges |
| LC No | 156 |
| Railway (km) | 523/22-24 |
| Length Including Approaches | 629.08 |
| Width of ROB | 10.20 m |
| GAD Status | Not Approved |
| No of Lanes | 2 |
| Financial Details | |
|---|---|
| AS Amount(crores) | 22.51 |
| Funded By | KIIFB |
| Project Outlay(crores) | 33.19 |
| Work Progress Details | |||
|---|---|---|---|
| Current status | DPR approved on 06.08.2020 for an amount of Rs. 33.19Cr. On 11.07.2022, Railway had given in-principle approval for starting the land acquisition. LA requisition submitted to District Collector on 29.10.2022. 4(1) published on 26.07.2024. 11(1) notification published on 19.05.2025. 19(1) notification published on 12.03.2026. GAD was approved by Railways on 28.05.2026. | ||