General Details | |||
---|---|---|---|
Administrative Sanction | Order Number | Dated | Amount(crores) |
GO(Rt)No.718/2018/PWD | 19.04.2018 | 22.51 | |
District | Palakkad | ||
LAC | Malampuzha | ||
Location |
Project Details | |
---|---|
Category | Road Over Bridges |
LC No | 156 |
Railway (km) | 523/22-24 |
Length Including Approaches | 629.08 |
Width of ROB | 10.20 m |
GAD Status | Not Approved |
No of Lanes | 2 |
Financial Details | |
---|---|
AS Amount(crores) | 22.51 |
Funded By | KIIFB |
Project Outlay(crores) | 33.19 |
Work Progress Details | |||
---|---|---|---|
Current status | DPR approved on 06.08.2020 for an amount of Rs. 33.19 Cr. After several revisions, final GAD submitted to Railways on 31.08.2021. Reminder letter send on 30.06.2022. On 11.07.2022, Railway had given in-principle approval for starting the land acquisition. LA requisition submitted to District Collector on 29.10.2022. LAO is appointed. Boundary stone planting completed. Joint inspection conducted on 08.02.2023. |