Moru Glass Gate ROB

Back

General Details
Administrative Sanction Order Number Dated Amount(crores)
GO(Rt)No.718/2018/PWD 19.04.2018 22.51
District Palakkad
LAC Malampuzha
Location
Project Details
Category Road Over Bridges
LC No 156
Railway (km) 523/22-24
Length Including Approaches 629.08
Width of ROB 10.20 m
GAD Status Not Approved
No of Lanes 2
Financial Details
AS Amount(crores) 22.51
Funded By KIIFB
Project Outlay(crores) 33.19
Work Progress Details
Current status DPR approved on 06.08.2020 for an amount of Rs. 33.19 Cr. After several revisions, final GAD submitted to Railways on 31.08.2021. Reminder letter send on 30.06.2022. On 11.07.2022, Railway had given in-principle approval for starting the land acquisition. LA requisition submitted to District Collector on 29.10.2022. LAO is appointed. Boundary stone planting completed. Joint inspection conducted on 08.02.2023.