The DPR for the Manjeshwar ROB was approved by KIIFB on 09.08.2020 for an amount of Rs. 40.40 Cr. GAD approved on 30.08.2025.
Manjeshwar ROB requires 224.28 cents of land. LA plan prepared and requisition
submitted to District Collector on 02.05.2024. Alignment stones laid and joint inspection
conducted on 05.03.2025; 12 stones displaced due to public protest. 6(1) notification
published on 13.06.2025. During joint site inspection, 14 stones found missing and all 14
stones replanted on 25.07.2025; revised drawings submitted. Contingency fund requested
on 01.09.2025 and forwarded to KIIFB. Payment released on 02.12.2025 and to be
transferred to Tahsildar. On 14.01.2026, another joint site inspection was conducted,