| General Details | |||
|---|---|---|---|
| Administrative Sanction | Order Number | Dated | Amount(crores) |
| GO(Rt)No.718/2018/PWD | 19.04.2018 | 22.51 | |
| District | Kozhikode | ||
| LAC | Koyilandy | ||
| Location | |||
| Project Details | |
|---|---|
| Actual Start Date | 19.04.2018 |
| Project Management Consultant | ISA |
| Category | Road Over Bridges |
| LC No | 204 |
| Railway (km) | 690/600-700 |
| Length Including Approaches | 410.11m |
| Width of ROB | 10.20 m |
| GAD Status | Not Approved |
| No of Lanes | 2 |
| Financial Details | |
|---|---|
| AS Amount(crores) | 22.51 |
| Funded By | Government |
| Project Outlay(crores) | 28.39 |
| Work Progress Details | |||
|---|---|---|---|
| Physical progress | 74 % | ||
| Current status | The DPR was approved by KIIFB on 09.08.2020 for an amount of Rs. 28.39 crore. LA delayed due to Semi High Speed Rail Project of KRDCL and GAD approval. The revised GAD was submitted on 03.10.2023. In the meeting conducted with the Kozhikode District Collector and Railways on 24.05.2025, it was decided to construct the Nelliyady ROB and provide connectivity to Muchukunnu through a service road. In-principle approval for the GAD was received on 29.04.2026. | ||