General Details | |||
---|---|---|---|
Administrative Sanction | Order Number | Dated | Amount(crores) |
GO(Rt)No.718/2018/PWD | 19.04.2018 | 22.51 | |
District | Ernakulam | ||
LAC | Piravom |
Project Details | |
---|---|
Category | Road Over Bridges |
LC No | 11 |
Railway (km) | 13/500-600 |
Length Including Approaches | 428.17m |
Width of ROB | 10.20 m |
GAD Status | Approved |
No of Lanes | 2 |
Financial Details | |
---|---|
AS Amount(crores) | 22.51 |
Funded By | KIIFB |
Project Outlay(crores) | 36.89 |
Work Progress Details | |||
---|---|---|---|
Current status | DPR approved by KIIFB on 31.07.2020. GAD approved on 25-07-2022. LA requisition submitted to Dist. Collector on 22.09.2022. Boundary stone planting completed & Joint inspection conducted on 28.11.2022. 4(1) notification published on 06.02.2023. SIA public hearing conducted on 20.03.2023. SIA final report submitted. Expert committee report was submitted to Dist. collector. Awaiting 11(1) notification. Awaiting for RR package approval. Structural valuation to be completed. |