Current status |
DPR approved by KIIFB on 09.08.2020 for an amount of Rs.38.56 Cr. LA to be taken up after getting approval of GAD from railways.
Project was pending due to Semi High Speed Rail project of KRDCL. Railways directed to submit revised GAD for all ROBs long pending due to Silver line vide letter dated 14.03.2023.
LUS inspection conducted on 04.07.2023 and report received. GAD submitted to Railways on 11.12.2023 for approval. Reminder letter sent on 04.06.2024 & 22.08.2024. As the work has been transferred from CAO/CN/ERS, a letter was submitted to CE/CN/RSP on 02.06.2025 to approveĀ theĀ GAD. |