Projects

PAYYOLI KOTTAKKAL ROB

Back

General Details
Administrative Sanction Order Number Dated Amount(crores)
GO(Rt)No.718/2018/PWD 19.04.2018 22.51
District Kozhikode
LAC Koyilandy
Project Details
Project Management Consultant ISA
Category Road Over Bridges
LC No 211
Railway (km) 701/700-800
Length Including Approaches 348.28 m
Width of ROB 10.20 m
GAD Status Not Approved
No of Lanes 2
Financial Details
AS Amount(crores) 22.51
Funded By KIIFB
Project Outlay(crores) 28.57
Work Progress Details
Current status DPR approved on 09.08.2020. LA plan under preparation. LA to be taken up after getting approval of GAD from railways. GAD submitted to Railways for approval.