Nellayi Gate ROB

Back

General Details
Administrative Sanction Order Number Dated Amount(crores)
GO(Rt)No.718/2018/PWD 19.04.2018 22.51
District Thrissur
LAC Puthukkad
Project Details
Actual Start Date 19.04.2018
Project Management Consultant ISA
Category Road Over Bridges
LC No 32
Railway (km) 50/100-200
Length Including Approaches 473.61 m
Width of ROB 10.20
GAD Status Not Approved
No of Lanes 2
Financial Details
AS Amount(crores) 22.51
Funded By KIIFB
Project Outlay(crores) 32.35
Work Progress Details
Physical progress 60 %
Current status DPR approved by KIIFB on 04.09.2021. LA to be taken up after getting approval of GAD from railways. Vide letter dated 11.07.2022, Railway informed that GAD of ROB’s between Ernakulam and Shornur will be approved only after finalization of 3rd line. Alignment of the 3rd and 4th lines has been received from the Railways. Upon revising the GAD and alignment, it was observed that several existing and proposed structures are affected. Therefore, following a site visit, a revised proposal with improved geometry was submitted to the Railways on 17.05.2026. If found agreeable, a topographical survey will be conducted and the alignment will be finalized accordingly.