General Details | |||
---|---|---|---|
Administrative Sanction | Order Number | Dated | Amount(crores) |
GO(Rt)No.718/2018/PWD | 19.04.2018 | 22.51 | |
District | Thrissur | ||
LAC | Puthukkad |
Project Details | |
---|---|
Actual Start Date | 19.04.2018 |
Project Management Consultant | ISA |
Category | Road Over Bridges |
LC No | 32 |
Railway (km) | 50/100-200 |
Length Including Approaches | 473.61 m |
Width of ROB | 10.20 |
GAD Status | Not Approved |
No of Lanes | 2 |
Financial Details | |
---|---|
AS Amount(crores) | 22.51 |
Funded By | KIIFB |
Project Outlay(crores) | 32.35 |
Work Progress Details | |||
---|---|---|---|
Physical progress | 60 % | ||
Current status | DPR approved by KIIFB on 04.09.2021. LA to be taken up after getting approval of GAD from railways. Final GAD submitted to Railways on 17.02.2022. Vide letter dated 11.07.2022, Railway informed that GAD of ROB’s between Ernakulam and Shornur will be approved only after finalization of 3rd line. Joint Site inspection held on 10.10.2023 along with Railways. Awaiting confirmation from Railway on alignment of 3rd and 4th Line. |