Projects

Nalukody ROB

Back

General Details
Administrative Sanction Order Number Dated Amount(crores)
GO(Rt)No.718/2018/PWD 19.04.2018 22.51
Revised Administrative Sanction Order Number Dated Amount(crores)
GO(Rt)No.46/2021/PWD 13.01.2021 41.02
District Kottayam
LAC Changanassery
Project Details
Project Management Consultant ISA
Category Road Over Bridges
LC No 7
Railway (km) 81/800-900
Length Including Approaches 476.93 M
Width of ROB 10.20
GAD Status Approved
No of Lanes 2
Financial Details
AS Amount(crores) 22.51
Revised AS Amount(crores) 41.02
Funded By KIIFB
Project Outlay(crores) 39.09
Work Progress Details
Current status DPR approved by KIIFB on 04.09.2021 for an amount of Rs.39.09 Cr. GAD was approved by Railways on 26.02.2022. LA requisition submitted to District Collector Kottayam on 13.04.2022. Revenue Sanction for LA received as per G.O.( Rt) No. 2082/2022/RD dated 07.05.2022. 6(1) notification published on 06.06.2022. Boundary Stone planting completed and Joint Inspection was conducted on 05.07.2022. Contingency charges of 10 Lakhs was received from KIIFB and remitted to LAO on 16.09.2022. 4(1) published on 22.10.2022. SIA public hearing conducted on 26.11.2022. Expert committee visited the site on 31.01.2023 and report submitted. 11(1) notification published on 01.06.2023. Survey completed. Invited Quotation for Structural valuation on 02/03/2024. Requotation for structural valuation invited on 15/03/2024.