General Details | |||
---|---|---|---|
Administrative Sanction | Order Number | Dated | Amount(crores) |
GO(Rt)No.718/2018/PWD | 19.04.2018 | 22.51 | |
Revised Administrative Sanction | Order Number | Dated | Amount(crores) |
GO(Rt)No.46/2021/PWD | 13.01.2021 | 41.02 | |
District | Kottayam | ||
LAC | Changanassery |
Project Details | |
---|---|
Project Management Consultant | ISA |
Category | Road Over Bridges |
LC No | 7 |
Railway (km) | 81/800-900 |
Length Including Approaches | 476.93 M |
Width of ROB | 10.20 |
GAD Status | Approved |
No of Lanes | 2 |
Financial Details | |
---|---|
AS Amount(crores) | 22.51 |
Revised AS Amount(crores) | 41.02 |
Funded By | KIIFB |
Project Outlay(crores) | 39.09 |
Work Progress Details | |||
---|---|---|---|
Current status | DPR approved by KIIFB on 04.09.2021. GAD approved by Railways on 26.02.2022. LA requisition submitted to DC, Kottayam on 13.04.2022. Boundary Stone planting completed and Joint Inspection conducted on 05.07.2022. 11(1) notification published on 01.06.2023. LA fund of Rs. 4,41,49,471/- transferred to LAO. 19(1) notification published on 09.01.2025. Award enquiry completed. |