General Details | |||
---|---|---|---|
Administrative Sanction | Order Number | Dated | Amount(crores) |
GO(Rt)No.718/2018/PWD | 19.04.2018 | 22.51 | |
District | Alappuzha | ||
LAC | Aroor | ||
Location |
Project Details | |
---|---|
Actual Start Date | 19.04.2018 |
Project Management Consultant | KITCO Ltd |
Category | Road Over Bridges |
LC No | 17 |
Railway (km) | 18/0-100 |
Length Including Approaches | 765.46 m |
Width of ROB | 9.75 m |
GAD Status | Not Approved |
No of Lanes | 2 |
Financial Details | |
---|---|
AS Amount(crores) | 22.51 |
Funded By | KIIFB |
Work Progress Details | |||
---|---|---|---|
Physical progress | 57 % | ||
Current status | RBDCK had prepared DPR and submitted to KIIFB for approval. KIIFB had requested to revise the DPR with the alignment on existing road on 10.09.2021. Accordingly after several discussions and meetings, revised DPR has been prepared and submitted to KIIFB on 22.01.2025 and GAD submitted to Railways on 04/03/2025 for approval. |