| General Details | |||
|---|---|---|---|
| Administrative Sanction | Order Number | Dated | Amount(crores) |
| GO(Rt)No.718/2018/PWD | 19.04.2018 | 22.51 | |
| Revised Administrative Sanction | Order Number | Dated | Amount(crores) |
| GO(Rt)No.46/2021/PWD | 13.01.2021 | 37.16 | |
| District | Thiruvananthapuram | ||
| LAC | Varkala | ||
| Location | |||
| Project Details | |
|---|---|
| Category | Road Over Bridges |
| LC No | 558 |
| Railway (km) | 177/800-900 |
| Length Including Approaches | 342.32 m |
| Width of ROB | 10.20 m |
| GAD Status | Approved |
| No of Lanes | 2 |
| Financial Details | |
|---|---|
| AS Amount(crores) | 22.51 |
| Revised AS Amount(crores) | 37.16 |
| Funded By | KIIFB |
| Project Outlay(crores) | 36.88 |
| Work Progress Details | |||
|---|---|---|---|
| Current status | DPR approved by KIIFB on 20.03.2022 for an amount of Rs.36.88 Cr. GAD approved by Railways on 08.08.2022. LA requisition submitted to District Collector on 12.12.2022. 6(1) notification published on 27.03.2023. Boundary stone planting completed & Joint inspection is conducted. Contingency charge released on 19.08.2023. 4(1) notification published on 26/10/2023 & SIA study completed. Expert committee report submitted to Dist. Collector. 11(1) published on 07.08.2024. LA fund submitted to LA Tahsildar KIIFB. Building valuation work in progress. | ||