Current status |
DPR approved by KIIFB for an amount of Rs.53.91 Cr on 20.03.2022. LA to be taken up after getting approval of GAD from railways.
Project was pending due to Semi High Speed Rail project of KRDCL. On 06.12.2022, KRDCL had informed to go ahead with the construction of ROBs without considering the silver line alignment and RBDCK intimated the same to Railways on 08.12.2022. Railways directed to submit revised GAD for all ROBs long pending due to Silver line vide letter dated 14.03.2023.
LUS inspection with Railways conducted on 04.07.2023 & Report received. Revised GAD submitted to Railways on 10.07.2023. On 30.08.2024, RBDCK had requested Railways to grant permission to start the LA process. |