Ollur Main Gate ROB

Back

General Details
Administrative Sanction Order Number Dated Amount(crores)
GO(Rt)No.718/2018/PWD 19.04.2018 22.51
District Thrissur
LAC Ollur
Project Details
Actual Start Date 19.04.2018
Project Management Consultant ISA
Category Road Over Bridges
LC No 26
Railway (km) 39/13-14
Length Including Approaches NOT FINALISED
Width of ROB NOT FINALISED
GAD Status NOT FINALISED
No of Lanes NOT FINALISED
Financial Details
AS Amount(crores) 22.51
Funded By KIIFB
Work Progress Details
Physical progress 30 %
Current status Consultant for DPR preparation appointed on 24.08.2018. But the proposed ROB at Ollur is not acceptable to public as there is 1 ROB and 1 underpass nearby. Therefore, Dist. Collector on 09.11.2021 directed Tahsildar to submit a report regarding the necessity of Ollur ROB. Tahsildar submitted the report to District Collector and based on the report District Collector has informed Special Secretary PWD that the necessity of the project to be re-examined vide letter dated 19.03.2022. Now, Secretary PWD has directed RBDCK to submit a report regarding the same. RBDCK submitted the report on 27.05.2022 and requested to convene a meeting in the presence of Hon’ble MLA, stake holders & public to discuss the matter regarding the closure of Railway gate.