Current status |
Consultant for DPR preparation appointed on 24.08.2018. But the proposed ROB at Ollur is not acceptable to public as there is 1 ROB and 1 underpass nearby. Therefore, Dist. Collector on 09.11.2021 directed Tahsildar to submit a report regarding the necessity of Ollur ROB. Tahsildar submitted the report to District Collector and based on the report District Collector has informed Special Secretary PWD that the necessity of the project to be re-examined vide letter dated 19.03.2022. Now, Secretary PWD has directed RBDCK to submit a report regarding the same. RBDCK submitted the report on 27.05.2022 and requested to convene a meeting in the presence of Hon’ble MLA, stake holders & public to discuss the matter regarding the closure of Railway gate. |