General Details | |||
---|---|---|---|
Administrative Sanction | Order Number | Dated | Amount(crores) |
GO(Rt)No.718/2018/PWD | 19.04.2018 | 22.51 | |
District | Thiruvananthapuram | ||
LAC | Chirayinkeezhu | ||
Location |
Project Details | |
---|---|
Actual Start Date | 19.04.2018 |
Project Management Consultant | ISA |
Category | Road Over Bridges |
LC No | 569 |
Railway (km) | 192/800-900 |
Length Including Approaches | NOT FINALISED |
Width of ROB | NOT FINALISED |
GAD Status | NOT FINALISED |
No of Lanes | NOT FINALISED |
Financial Details | |
---|---|
AS Amount(crores) | 22.51 |
Funded By | KIIFB |
Work Progress Details | |||
---|---|---|---|
Physical progress | 30 % | ||
Current status | A single ROB alignment was prepared in between Sarkara & Manjadimoodu level cross and forwarded to Railways for their concurrence on 20.05.2022. In the mean time Letter had issued to ISA for examine/modify the independent alignments through existing road. Independent alignments was submitted by M/s ISA on 22.08.2022 and is under scrutiny. Now Railway had informed that the single ROB proposal is feasible at site and instructed to submit the GAD along with alignment. Appointed Consultant M/s RITES for DPR preparation on 17.03.2023. |