Current status |
Alignment was prepared but the project will severely affect English India Clays Ltd. The EICL company is not agreeing the alignment prepared and the same was intimated with Secretary, PWD on 30.07.2020. Alignment is put on hold. On 19.07.2022, RBDCK directed consultant to study an alternative alignment. Vide letter dated 23.11.2022, RBDCK requested EICL to inform a convenient date for meeting. A meeting was convened by VSCC in presence of MLA and Counsellors on 24.12.2022 and another meeting was conducted with VSCC and EICL on 27.12.2022. It was decided to proceed with small modification in the latest alignment prepared.
Appointed Consultant M/s RITES for DPR preparation on 17.03.2023 & GAD submitted to Railways on 10/11/2023 for approval. Joint inspection as requested by Railways conducted on 11/03/2024. Railways informed that GAD may be considered only after completing the feasibility study for increasing sectional speed. |