Current status |
Alignment will be finalized after the approval of GAD from Railways. GAD is submitted to Railways for approval.
Project was pending due to Semi High Speed Rail project of KRDCL. On 06.12.2022, KRDCL had informed to go ahead with the construction of ROBs without considering the silver line alignment and RBDCK intimated the same to Railways on 08.12.2022. Railways directed to submit revised GAD for all ROBs long pending due to Silver line vide letter dated 14.03.2023.
Appointed Consultant M/s RITES for DPR preparation on 17.03.2023. GAD submitted to Railways on 27/09/2023. GAD returned for corrections and revised GAD was submitted to Railways on 07.02.2024. In principle approval obtained for GAD for DPR preparation. DPR under preparation. |