Current status |
DPR submitted to KIIFB on 30.06.2021.
In CMT Meeting of Tirur LAC on 24.01.2022, MLA proposed to increase the length of flyover to a avoid junction. A Joint Inspection was conducted with MLA on 04.02.2022. As directed by MLA, draft cost escalation due to this proposal submitted to MLA on 22.02.2022. ED KIIFB directed to continue with the existing alignment during the Joint Inspection on 17.03.2022. The matter was informed to Honourable MLA. The same was agreed by MLA on 17-05-2022. Compliance report on TAR was submitted on 18.05.2022. TAR 2 was issued by KIIFB on 09.06.2022 and Compliance report was submitted to KIIFB on 25.07.2022.
KIIFB had requested permission from Govt. to stop the work temporarily due to shortage of fund. In Tirur LAC meeting conducted by KIIFB in the presence of Hon. MLA on 27.12.2022, CEO KIIFB informed that the project may be deferred for the time being. |