General Details
Administrative Sanction Order Number Dated Amount(crores)
GO(Rt)No.942/2017/PWD 10.07.2017 40
District Kasargod
LAC Kanhangad
Project Details
Actual Start Date 10.07.2017
Project Management Consultant E I Technologies
Category Flyover
Length including approaches 1710 m
Width of Flyover 9.00m
No of Lanes 2
Financial Details
AS Amount(crores) 40
Funded By KIIFB
Work Progress Details
Physical progress 22 %
Current status DPR submitted to KIIFB on 20.10.2021. DPR under KIIFB appraisal.