General Details | |||
---|---|---|---|
Administrative Sanction | Order Number | Dated | Amount(crores) |
GO(Rt)No.1324/2016/PWD | 27.09.2016 | 10 | |
District | Kozhikode | ||
LAC | Kunnamangalam |
Project Details | |
---|---|
Project Management Consultant | KITCO Ltd |
Category | Road Projects |
Length | NOT FINALISED |
Right of way | NOT FINALISED |
No of Lanes | NOT FINALISED |
Financial Details | |
---|---|
AS Amount(crores) | 10 |
Funded By | KIIFB |
Work Progress Details | |||
---|---|---|---|
Current status | Govt suggested 2.5 Km Bypass. RBDCK suggested an additional 1.1 Km and submitted concept report to Govt. Govt instructed to submit DPR. Direction given to KITCO for preparing concept report and approx. cost for a bypass with all 3 links as suggested by govt. Concept report submitted to govt on 01.10.2019. |