DPR Preparation For Champanoor ROB

Back

General Details
Administrative Sanction Order Number Dated Amount(crores)
GO(Rt)No.788/2020/PWD 30.09.2020 0.07
District Ernakulam
LAC Angamaly
Location
Project Details
Actual Start Date 30.09.2020
Category Road Over Bridges
LC No 61
Railway (km) 78/2-3
Length Including Approaches Not Finalized
Width of ROB Not Finalized
GAD Status Not Finalized
No of Lanes Not Finalized
Financial Details
AS Amount(crores) 0.07
Funded By Govt Funded
Work Progress Details
Physical progress 17 %
Current status LOA issued to M/s KITCO for Alignment Study and DPR preparation on 30.12.2021 and agreement was executed. The consultant submitted the concept report. Vide letter dated 11.07.2022, Railway informed that GAD of ROB’s between Ernakulam and Shornur will be approved only after finalisation of 3rd line. Joint inspection with Railways conducted on 07/03/2024. Revised concept report preparation under progressing by consultant.