Current status |
DPR approved by KIIFB on 21.12.2020 for an amount of Rs.43.29 Cr for land acquisition and Rs.50.67 Cr for construction on 15.03.2022. LA requisition submitted to DC, TVM on 10.09.2021. 6(1) notification published on 29.10.2021. Contingency charge of Rs. 50 lakhs released to LAO on 13.01.2022. Final alignment sketch was submitted to LAO on 21.05.2022 and site inspection was conducted on 26.05.2022. 4(1) notification published on 26.07.2022. SIA public hearing conducted on 31.10.2022. Expert Committee report approved by District Collector and appropriate govt. order issued under section 8(2) on 05.01.2023. 11(1) notification published on 10.02.2023. Hearing conducted on 21.03.2023. Structural valuation completed and informed to LAO. Joint inspection of RBDCK with KIIFB & KWA conducted on 04.08.2023 regarding utility shifting of KWA. As per the meeting decision, GPR Survey conducted on 30/10/2023. LA fund request submitted to KIIFB on 11.10.2023 but, KIIFB returned the same & requested to submit the BVR and RR statement or draft DVS in support of the claim. Awaiting BVR & DVS from LAO. As requested by the LAO, the entire amount for acquisition has been transferred to the Revenue department. The revised GAD as per the GPR survey output is sent to SE KWA for concurrence & GM KIIFB for reference. 19(1) published partially on 05/07/2024. Award Enquiry Ongoing. |