Kariyannoor-Susheelapadi ROB

Back

General Details
Administrative Sanction Order Number Dated Amount(crores)
GO (Rt) No.1324/2016/PWD 27.09.2016 10
Revised Administrative Sanction Order Number Dated Amount(crores)
GO (Rt) No. 39/2021/PWD 03.09.2021 40.12
District Palakkad
LAC Thrithala
Project Details
Category Road Over Bridges
Financial Details
AS Amount(crores) 10
Revised AS Amount(crores) 40.12
Funded By KIIFB
Work Progress Details
Current status Financial sanction accorded by KIIFB for an amount of Rs.32.91Cr for the construction of ROB at Susheelapady only vide order no. PWD005-14/TE-1/2022/KIIFB dated 04.08.2022. KIIFB informed that Kariyanoor proposal shall be considered once the approach road is developed and necessary approval from railways are obtained. We had informed the matter to Hon’ble Minister of LSGD and accordingly a site inspection was conducted on 19.08.2022 in the presence of Hon’ble Minister and local people representatives. Hon’ble Minister had directed to conduct a survey of existing road and prepare a draft plan for widening of the existing road. We had completed the survey and a meeting was conducted with panchayath officials on 01.11.2022 and the drawing was submitted to the Panchayat officials for further necessary actions. Susheelappadi ROB - Vide Letter No. J/W.352/G dated 08.11.2022 DEN/EAST/PGT had instructed to conduct a joint feasibility inspection with Asst. Divisional Engineer/Shornur and submit the joint feasibility report for further necessary action. Accordingly a joint site inspection was conducted along with railway and RBDCK officials on 30.11.2022 and the railway had submitted the land plan on 23.12.2022. Revised GAD submitted to railway on 25.03.2023. Reminder submitted on 18.05.2023. P&E charges released to Railways on 09.10.2023. On 27.11.2023, Railways had given permission to start the LA Process and LA requisition submitted on 15.01.2024. Revised GAD submitted to Railways on 20.02.2024. Sp. Tahsildar LA Palakkad has been appointed as LAO on 11/06/2024. Boundary stone planting completed on 28.07.2024. Joint inspection with LAO has also been completed, contingency charge was released to LAO on 04.09.2024.