Current status |
Vide GO. (Rt.) No. 1141/2022/PWD dated 21.11.2022, the Government of Kerala has appointed RBDCK Ltd. as the Implementing Agency for the Construction of ROB . RBDCK requested GoK for the sanctioning of Rs. 10 lakhs for the preparation of DPR on 02.12.2022. GoK accorded the AS for preparation of DPR at a cost of Rs.7 lakh+ 18% GST vide G.O.(Rt)No.109/2023/PWD dt. 03.02.2023. Appointed consultant M/s RITES for DPR preparation. Alignment approved on 01.08.2023. GAD submitted to railways on 01.08.2023. Traffic Study completed on 17.09.2023. DPR is under preparation. Request Submitted to Railways for Joint Inspection for LUS on 11.10.2023. Joint Inspection conducted on 24.11.2023. GAD submitted to Railways on 19.01.2024. GAD was returned by Railways on 23.01.2024. Requested Railways for a meeting and GAD will be submitted after the meeting. |