Current status |
Appointed consultant M/s RITES for DPR preparation. GAD submitted to Railways on 20/02/2024. Site inspection with SSE Railways conducted on 30/05/2024. GAD returned to RBDCK by the railways for incorporating corrections. Corrected GAD submitted to Railways on 15.10.2024. Again joint inspection conducted on 23.01.2025 and decided to conduct soil investigation. Revised GAD with soil report submitted to Railways on 28.04.2025.Awaiting approval from Railways. Also, requested to inform the P& E charge amount. Requested ADEN,Thrissur(Southern railways) to intimate a convenient date for joint inspection, as directed by DRM/(Southern railways). |