General Details | |||
---|---|---|---|
Administrative Sanction | Order Number | Dated | Amount(crores) |
GO(Rt)No.1324/2016/PWD | 27.09.2016 | 20 | |
Technical Sanction | Order Number | Dated | Amount(crores) |
RBDCK/T 301/TS-18/2021-22 | 18.10.2021 | 23.87 | |
Revised Administrative Sanction | Order Number | Dated | Amount(crores) |
G.O. (Rt)No.700/2017/PWD | 24.05.2017 | 34.16 | |
District | Malappuram | ||
LAC | Tanur | ||
Location |
Project Details | |
---|---|
Actual Start Date | 04.01.2021 |
Contractor(s) | M/s SPL Infrastructure Pvt. Ltd |
Project Management Consultant | RITES |
Category | Road Over Bridges |
LC No | 172-A |
Railway (km) | 632/000-100 |
Length Including Approaches | 406.69m |
Width of ROB | 10.15m |
GAD Status | APPROVED |
No of Lanes | 2 |
Financial Details | |
---|---|
AS Amount(crores) | 20 |
Revised AS Amount(crores) | 34.16 |
Funded By | KIIFB |
Project Outlay(crores) | 31.31 |
TS Amount(crores) | 23.87 |
Tender Details | |||
---|---|---|---|
Tender No | Dated | Tender Amount(crores) | RBDCK/ROB/T301/ROB/14 | 25.06.2020 | 222.7 |
Agreement Details | |||||||
---|---|---|---|---|---|---|---|
Agreement No | Agreement Date | Agreed Amount(crores) | Site Handover Date | Period of Completion | Actual Date of Completion | ||
RBDCK/ROB/T44/28/2021 | 04.01.2021 | 251.48 | 12 Months |
Work Progress Details | |||
---|---|---|---|
Physical progress | 63 % | ||
Current status | All Foundation and substructure completed including Pier cap. Deck slab 6/10 completed (except Railway adjacent span). Adjacent span may be executed only after Railway span Girder erection. Girder erection completed except adjacent span. Drainage, Retaining wall & Service road works are progressing. Railway portion - Pile, Pile cap, Pier & pier cap works are completed. Super structure works to be executed by Railways. |