Projects

Chirayinkeezhu ROB

Back View Progress

General Details
Administrative Sanction Order Number Dated Amount(crores)
GO(Rt)No.1324/2016/PWD 27.09.2016 10
Technical Sanction Order Number Dated Amount(crores)
RBDCK/T 301/TS-13/2021-22 18.10.2021 26.16
Revised Administrative Sanction Order Number Dated Amount(crores)
GO(Rt)No.884/2017/PWD 25.06.2017 26.21
District Thiruvananthapuram
LAC Chirayinkeezhu
Location
Project Details
Actual Start Date 04.01.2021
Contractor(s) M/s SPL Infrastructure Pvt. Ltd
Project Management Consultant RITES
Category Road Over Bridges
LC No 566
Railway (km) 191/400-500
Length Including Approaches 394.00
Width of ROB 10.70
GAD Status APPROVED
No of Lanes 2
Financial Details
AS Amount(crores) 10
Revised AS Amount(crores) 26.21
Funded By KIIFB
Project Outlay(crores) 25.08
TS Amount(crores) 26.16
Tender Details
Tender No Dated Tender Amount(crores)
RBDCK/ROB/T301/ROB/14 25.06.2020 222.7
Agreement Details
Agreement No Agreement Date Agreed Amount(crores) Site Handover Date Period of Completion Actual Date of Completion
RBDCK/ROB/T44/28/2021 04.01.2021 251.48 25.01.2018 12 Months
Work Progress Details
Physical progress 51 %
Current status All Foundation and substructure completed up to Pier cap. Abutment Wall and Girder erection completed except adjacent span. Drain and Retaining wall work at A1(LHS &RHS), A2 RHS and A2 LHS 39/93 meter completed. Remaining Retaining wall works were holded by Railways till 24/05/2024. Deck slab sheet laying and reinforcement works are progressing. 3/11 deck slab concreting completed. Remaining works started on 06.08.2024. Railway Portion - (Foundation , substructure and superstructure will be directly done by Railways) - Pile, pile cap, pier and pier cap completed. 3 out of 3 Girder erection completed. Deck slab work under progress.
View Progress