General Details | |||
---|---|---|---|
Administrative Sanction | Order Number | Dated | Amount(crores) |
GO(Rt)No.1324/2016/PWD | 27.09.2016 | 10 | |
Technical Sanction | Order Number | Dated | Amount(crores) |
RBDCK/T 301/TS-13/2021-22 | 18.10.2021 | 26.16 | |
Revised Administrative Sanction | Order Number | Dated | Amount(crores) |
GO(Rt)No.884/2017/PWD | 25.06.2017 | 26.21 | |
District | Thiruvananthapuram | ||
LAC | Chirayinkeezhu | ||
Location |
Project Details | |
---|---|
Actual Start Date | 04.01.2021 |
Contractor(s) | M/s SPL Infrastructure Pvt. Ltd |
Project Management Consultant | RITES |
Category | Road Over Bridges |
LC No | 566 |
Railway (km) | 191/400-500 |
Length Including Approaches | 394.00 |
Width of ROB | 10.70 |
GAD Status | APPROVED |
No of Lanes | 2 |
Financial Details | |
---|---|
AS Amount(crores) | 10 |
Revised AS Amount(crores) | 26.21 |
Funded By | KIIFB |
Project Outlay(crores) | 25.08 |
TS Amount(crores) | 26.16 |
Tender Details | |||
---|---|---|---|
Tender No | Dated | Tender Amount(crores) | RBDCK/ROB/T301/ROB/14 | 25.06.2020 | 222.7 |
Agreement Details | |||||||
---|---|---|---|---|---|---|---|
Agreement No | Agreement Date | Agreed Amount(crores) | Site Handover Date | Period of Completion | Actual Date of Completion | ||
RBDCK/ROB/T44/28/2021 | 04.01.2021 | 251.48 | 25.01.2018 | 12 Months |
Work Progress Details | |||
---|---|---|---|
Physical progress | 51 % | ||
Current status | All Foundation and substructure completed up to Pier cap. Abutment Wall and Girder erection completed except adjacent span. Drain and Retaining wall work at A1(LHS &RHS), A2 RHS and A2 LHS 39/93 meter completed. Remaining Retaining wall works were holded by Railways till 24/05/2024. Deck slab sheet laying and reinforcement works are progressing. 3/11 deck slab concreting completed. Remaining works started on 06.08.2024. Railway Portion - (Foundation , substructure and superstructure will be directly done by Railways) - Pile, pile cap, pier and pier cap completed. 3 out of 3 Girder erection completed. Deck slab work under progress. |