Projects

Chirayinkeezhu ROB

Back View Progress

General Details
Administrative Sanction Order Number Dated Amount(crores)
GO(Rt)No.1324/2016/PWD 27.09.2016 10
Technical Sanction Order Number Dated Amount(crores)
RBDCK/T 301/TS-13/2021-22 18.10.2021 26.16
Revised Administrative Sanction Order Number Dated Amount(crores)
GO(Rt)No.884/2017/PWD 25.06.2017 26.21
District Thiruvananthapuram
LAC Chirayinkeezhu
Location
Project Details
Actual Start Date 04.01.2021
Contractor(s) M/s SPL Infrastructure Pvt. Ltd
Project Management Consultant RITES
Category Road Over Bridges
LC No 566
Railway (km) 191/400-500
Length Including Approaches 394.00
Width of ROB 10.70
GAD Status APPROVED
No of Lanes 2
Financial Details
AS Amount(crores) 10
Revised AS Amount(crores) 26.21
Funded By KIIFB
Project Outlay(crores) 25.08
TS Amount(crores) 26.16
Tender Details
Tender No Dated Tender Amount(crores)
RBDCK/ROB/T301/ROB/14 25.06.2020 222.7
Agreement Details
Agreement No Agreement Date Agreed Amount(crores) Site Handover Date Period of Completion Actual Date of Completion
RBDCK/ROB/T44/28/2021 04.01.2021 251.48 25.01.2018 12 Months
Work Progress Details
Physical progress 62 %
Current status All foundation and substructure works completed upto pier cap. Abutment wall and girder erection except adjacent span completed. Retaining wall work completed and embankment filling under progress. Drain work at A1 side RHS 25% and LHS 40% completed. At A2 side RHS 96% completed and remaining works are under progress. 6/11 deck slab concreting completed. Remaining deck slab sheet laying, reinforcement and concrete works under progress. Railway Portion - (Foundation , substructure and superstructure will be directly done by Railways) - Pile, pile cap, pier and pier cap completed. 3 out of 3 Girder erection completed. Deck slab concreting works completed.
View Progress