Projects

Carithas ROB

Back

General Details
Administrative Sanction Order Number Dated Amount(crores)
GO (Rt) No. 1535/2011/PWD 09.11.2011 23.04
Technical Sanction Order Number Dated Amount(crores)
RBDCK/ T65/ TS-15/ 2019-20 28.09.2019 11.98
Revised Administrative Sanction Order Number Dated Amount(crores)
GO (Rt) No. 758/2019/PWD 21.06.2019 23.34
District Kottayam
LAC Ettumanoor
Location
Project Details
Actual Start Date 12.12.2022
Contractor(s) Uralungal Labour Contract Co-operative Society Ltd
Project Management Consultant RITES
Category Road Over Bridges
LC No 30
Railway (km) 52/600-700
Length Including Approaches 323.78
Width of ROB 7.50
GAD Status APPROVED
No of Lanes 2
Financial Details
AS Amount(crores) 23.04
Revised AS Amount(crores) 23.34
Funded By Govt Funded
Project Outlay(crores) 23.34
TS Amount(crores) 11.98
Tender Details
Tender No Dated Tender Amount(crores)
RBDCK/ROB/T65/164/2022 06.04.2022 10.55
Agreement Details
Agreement No Agreement Date Agreed Amount(crores) Site Handover Date Period of Completion Actual Date of Completion
RBDCK/T 65/ROB/ 67 /2022 08.12.2022 13.6 12.12.2022 15 months
Work Progress Details
Physical progress 65 %
Current status Pile, Pile cap, pier, pier cap works completed. 23/24 girder & 12/12 pedestal completed. 3/8 deck slab completed