General Details | |||
---|---|---|---|
Administrative Sanction | Order Number | Dated | Amount(crores) |
GO(Rt)No.1060/2013/PWD | 31.07.2013 | ||
Technical Sanction | Order Number | Dated | Amount(crores) |
RBDCK/T 105/TS-24/2021-22 | 30.03.2022 | 20.77 | |
Revised Administrative Sanction | Order Number | Dated | Amount(crores) |
G.O. (Rt) No. 227/2022/PWD | 02.03.2022 | 21.28 | |
District | Ernakulam | ||
LAC | Piravom | ||
Location |
Project Details | |
---|---|
Contractor(s) | M/s Cherian Varkey Construction Co. (P) Ltd |
Project Management Consultant | RITES |
Category | Road Over Bridges |
LC No | 12 |
Railway (km) | 16/200-300 |
Length Including Approaches | 464.16 |
Width of ROB | 7.50 |
GAD Status | RAILWAY PORTION COMPLETED |
No of Lanes | 2 |
Financial Details | |
---|---|
Revised AS Amount(crores) | 21.28 |
Funded By | Govt Funded |
Project Outlay(crores) | 21.28 |
TS Amount(crores) | 20.77 |
Tender Details | |||
---|---|---|---|
Tender No | Dated | Tender Amount(crores) | RBDCK/ROB/T105/162/2022 | 05.04.2022 | 17.28 |
Agreement Details | |||||||
---|---|---|---|---|---|---|---|
Agreement No | Agreement Date | Agreed Amount(crores) | Site Handover Date | Period of Completion | Actual Date of Completion | ||
RBDCK/T 105/ROB/73/2023 | 01.02.2023 | 20.59 | 28.12.2022 | 18 months |
Work Progress Details | |||
---|---|---|---|
Physical progress | 90 % | ||
Current status | All the works upto deck slab, handrail & crash barrier completed. WMM works Completed. |