Projects

MELECHOVHA UNDERPASS

Back View Alignment

General Details
Administrative Sanction Order Number Dated Amount(crores)
GO(Rt)No.1324/2016/PWD 27.09.2016 30
Revised Administrative Sanction Order Number Dated Amount(crores)
GO(Rt)No.1816/2017/PWD 04.12.2017 28.68
District Kannur
LAC Kannur
Project Details
Actual Start Date 17.02.2018
Project Management Consultant KITCO Ltd
Category Flyover
Length including approaches 320.00 m
Width of Flyover 10 m (Overall 24 m)
No of Lanes 2 Lane with service road on both side
Financial Details
AS Amount(crores) 30
Revised AS Amount(crores) 28.68
Funded By KIIFB
Project Outlay(crores) 27.59
Work Progress Details
Physical progress 89 %
Current status LA requisition submitted to Dt. Collector Kannur on 17.02.2018. LA is in final stage. BVR submitted to DC for approval on 25.11.2020. RR packages were approved by LRC. LA compensation request for Rs.15,08,72,120/- received and uploaded in the KIIFB portal on 23.06.2021. DVS submitted to DC for approval on 22.06.2021. 19(1) notification issued on 09.08.2021. Award enquiry completed on 09.09.2021. NH directed to start the project only after obtaining NOC from MORTH/NHAI. RBDCK submitted request to CE NH and GoK. GoK directed Regional Officer MORTH to initiate the process. RBDCK requested NHAI for NOC on 12.08.2021. NOC obtained from NHAI on 12.10.2021. Meanwhile in the joint site inspection conducted with KRFB officials, it is found that a slight change in the cental point is required in the joining point of the Kannur City Road improvement project. An extend of 0.0035 hectors of land is required to rectify the issue. Request submitted to KIIFB availing sanction for the same on 23.09.2021. Award approved on 30.11.2021., DC informed that the land will be taken possession within 15.01.2022.
View Alignment