South Bazar Flyover

Back View Alignments

General Details
Administrative Sanction Order Number Dated Amount(crores)
GO(Rt)No.1324/2016/PWD 27.09.2016 30
Revised Administrative Sanction Order Number Dated Amount(crores)
GO(Rt)No.1916/2017/PWD 23.12.2017 255.39
District Kannur
LAC Kannur
Project Details
Actual Start Date 04.01.2020
Project Management Consultant KITCO Ltd
Category Flyover
Length including approaches 1092
Width of Flyover 10.90
No of Lanes 4
Financial Details
AS Amount(crores) 30
Revised AS Amount(crores) 255.39
Funded By KIIFB
Project Outlay(crores) 130.87
Work Progress Details
Physical progress 64 %
Current status DPR approved on 06.09.2019 for an amount of Rs.130.87 Cr. LA requisition submitted to District Collector and AS obtained from Revenue department on 04.01.2020. 4(1) published on 25.11.2020. SIA final report published and expert committee report submitted. 11(1) notification published on 20.05.2021. BVR approved by District Collector on 10/08/2021. Rehabilitation and Resettlement package for affected families got finalized and submitted to Land Revenue Commissioner for approval on 24/11/2021. Structural Valuation completed. Fund request received from LAO and submitted to KIIFB on 11.02.2022. KIIFB released the amount and same was deposited to LAO on 01.04.2022. 19(1) declaration published on 19.05.2022. Land taking possession started on 15.12.2022 (65% taken possession completed). Currently, 28 cases have been filed in the High Court against land acquisition and their trial is ongoing. Apart from the above cases, steps are taken to acquire the rest of the land. Meanwhile, RBDCK requested KWA, KSEB and BSNL to submit utility shifting estimates and joint site inspection for the same was conducted on 13.10.2022. KWA, BSNL & KSEB was submitted the estimates respectively on 30.12.2022, 23.06.2023 & 11.07.2023.