Current status |
DPR approved on 06.09.2019 for an amount of Rs.130.87 Cr. LA requisition submitted to District Collector and AS obtained from Revenue department on 04.01.2020. 4(1) published on 25.11.2020. SIA final report published and expert committee report submitted. 11(1) notification published on 20.05.2021. BVR approved by District Collector on 10/08/2021. Rehabilitation and Resettlement package for affected families got finalized and submitted to Land Revenue Commissioner for approval on 24/11/2021. Structural Valuation completed. Fund request received from LAO and submitted to KIIFB on 11.02.2022. KIIFB released the amount and same was deposited to LAO on 01.04.2022. 19(1) declaration published on 19.05.2022. Land taking possession started on 15.12.2022 (77.83% taken possession completed). Currently, 35 cases (9 no. RBDCK not a respondent) have been filed in the High Court against land acquisition and their trial is ongoing. Now counter filed in all 26 cases.
Meanwhile, RBDCK requested KWA, KSEB and BSNL to submit utility shifting estimates and joint site inspection for the same was conducted on 13.10.2022. KWA, BSNL & KSEB has submitted the estimates respectively on 30.12.2022, 23.06.2023 & 11.07.2023.
Quotation invited for demolition of buildings (phase 1) on 04.04.2025, LOA issued on 24.04.2025. As the bidder not remit the bid amount re invited the quotation on 23.06.2025. |