Projects

South Bazar Flyover

Back View Alignments

General Details
Administrative Sanction Order Number Dated Amount(crores)
GO(Rt)No.1324/2016/PWD 27.09.2016 30
Revised Administrative Sanction Order Number Dated Amount(crores)
GO(Rt)No.1916/2017/PWD 23.12.2017 255.39
District Kannur
LAC Kannur
Project Details
Actual Start Date 04.01.2020
Project Management Consultant KITCO Ltd
Category Flyover
Length including approaches 1092
Width of Flyover 10.90
No of Lanes 4
Financial Details
AS Amount(crores) 30
Revised AS Amount(crores) 255.39
Funded By KIIFB
Project Outlay(crores) 130.87
Work Progress Details
Physical progress 64 %
Current status Stone planting completed on 29.10.2020. Joint site inspection completed on 12.11.2020. 4(1) published on 25.11.2020. 11(1) notification published on 14.05.2021. Structural Valuation completed. Fund request received from LAO and submitted to KIIFB on 11.02.2022. KIIFB released the amount and same was deposited to LAO on 01.04.2022. 19(1) declaration published on 19.05.2022. Land taking possession started on 15.12.2022 (55% taken possession completed). Currently, 21 cases have been filed in the High Court against land acquisition and their trial is ongoing. Apart from the above cases, steps are taken to acquire the rest of the land.
View Alignments