Purayar ROB

Back

General Details
Administrative Sanction Order Number Dated Amount(crores)
GO(Rt)No.1324/2016/PWD 27.09.2016 10
District Ernakulam
LAC Aluva
Project Details
Actual Start Date 14.06.2018
Project Management Consultant KITCO Ltd
Category Road Over Bridges
LC No 64B
Railway (km) 85/12-13
Length Including Approaches 916.80
Width of ROB 10.15
GAD Status Not approved
No of Lanes 2
Financial Details
AS Amount(crores) 10
Funded By KIIFB
Project Outlay(crores) 45.67
Work Progress Details
Physical progress 52 %
Current status LA requisition submitted on 28.06.2018. 11(1) Notification published on 03.03.2021. 19(1) declaration published on 22.02.2022. 20 out of 55 cases handed over to RBDCK on 07.02.2023. Balance cases has to be handed over to RBDCK from LAO. P & E charges released to Railways for further processing of GAD on 06.11.2020. After several revisions Railways directed to submit the GAD to CBE Chennai as this is a deposit work. Revised GAD submitted to CBE, Southern Railways, Chennai on 19.11.2021. Railways directed to submit the GAD along with the joint feasibility report. Joint inspection with Railways conducted on 24.01.2022& report and site sketch has been submitted to Railways on 03.02.2022. Again after several revisions, RBDCK submitted GAD on 07.03.2023. Railways also informed that ROBs between Ernakulam and Shornur can be taken up only after finalisation of the proposed 3rd Railway line between Ernakulam and Shornur.