Current status |
DPR approved by KIIFB on 29.06.2018 for an amount of Rs.437.28 Cr. LA requisition submitted to District Collector, Ernakulam on 27.10.2018.
Boundary stone planting completed and Joint site inspection conducted on 12.02.2021 and 15.02.2021. Letter sent to District Collector for giving instruction to handed over contingency charges to newly appointed LAO. Expert Committee report submitted to Government on 12.03.2021. 11(1) notification published on 25.02.2022. Land subdivision survey field work completed. Hearing on RR package conducted on 23.12.2022. 19(1) declaration to be published.
LA fund request received from LAO and the same submitted to KIIFB for release of payment. KIIFB released the payment and amount deposited to LAO. |