Kuttiyadi Bypass

Back

General Details
Administrative Sanction Order Number Dated Amount(crores)
GO(Rt)No.1324/2016/PWD 27.09.2016 10
District Kozhikode
LAC Kuttiady
Project Details
Actual Start Date 15.01.2019
Project Management Consultant KITCO Ltd
Category Road Projects
Length 1.462 km
Right of way 12 m
No of Lanes 2
Financial Details
AS Amount(crores) 10
Funded By KIIFB
Project Outlay(crores) 37.96
Work Progress Details
Physical progress 3 %
Current status Revised requisition submitted to DC, Kozhikode on 12.01.2021. As per the decision of District Collector revised alignment plan submitted to District Collector, Revenue AS obtained as per G.O.(Rt) No. 536/2012/RD dated 09.02.2021. Survey works for planting boundary stone again started and interrupted by public. WPC-5585/2021 filed by Shri. Krishnan Nair before Hon'ble HC for changing alignment on 01.03.2021. KIIFB has directed to revise the DPR for minor corrections. TS committee convened on 27.01.2022. TS Committee approved the modified alignment as per KIIFB TRC’s direction and same has been submitted to KIIFB for FS on 14.02.2022. A meeting was convened by Add. CEO KIIFB on 24.02.2022, and directed to proceed with stone laying procedures. A joint meeting was conducted on 08.03.2022, by MLA Kuttiyadi in the presence of panchayath representatives and stake holders and it was decided to start the boundary stone laying at the earliest. Boundary stone laying completed & Joint inspection conducted on 05.04.2022. 4(1) notification published on 30.05.2022. As requested by LAO, additional stones were planted and joint inspection conducted on 01.07.2022. SIA public hearing conducted on 25.08.2022. Expert committee report submitted to DC. 11(1) notification published on 12.01.2023. Survey work completed. Sub division survey works progressing.