General Details | |||
---|---|---|---|
Administrative Sanction | Order Number | Dated | Amount(crores) |
GO (Rt) No. 942/2017/PWD | 10.07.2017 | 50 | |
District | Kollam | ||
LAC | Eravipuram |
Project Details | |
---|---|
Project Management Consultant | KITCO Ltd |
Category | Road Over Bridges |
LC No | 77 |
Railway (km) | 151/300-400 |
Length Including Approaches | 387.60 |
Width of ROB | 10.20 |
GAD Status | Not approved |
No of Lanes | 2 |
Financial Details | |
---|---|
AS Amount(crores) | 50 |
Funded By | KIIFB |
Project Outlay(crores) | 30.93 |
Work Progress Details | |||
---|---|---|---|
Physical progress | 2 % | ||
Current status | DPR was approved by KIIFB on 18.03.2019 for an amount of Rs.30.93 Cr. LA requisition submitted on 04.10.2019. AS for LA GO(Rt) No 3108/2019/RD dt.30.10.2019. GAD approved by Railways on 22.09.2023. Request letter for NOC submitted to Regional Officer, NHAI, TVM on 04.05.2022. NOC issued by NHAI on 21.12.2024. LA requisition submitted to District collector on 05.02.2025. Revenue (B) sanction was received on 18.03.2025. Invited Quotation for planting boundary stone. |