General Details | |||
---|---|---|---|
Administrative Sanction | Order Number | Dated | Amount(crores) |
GO(Rt)No.1324/2016/PWD | 27.09.2016 | 50 | |
District | Ernakulam | ||
LAC | Ernakulam | ||
Location |
Project Details | |
---|---|
Actual Start Date | 15.02.2019 |
Project Management Consultant | KITCO Ltd |
Category | Road Over Bridges |
LC No | 75A |
Railway (km) | 108/6-7 |
Length Including Approaches | 523.92 |
Width of ROB | 20.00 |
GAD Status | Approved |
No of Lanes | 4 |
Financial Details | |
---|---|
AS Amount(crores) | 50 |
Funded By | KIIFB |
Project Outlay(crores) | 89.774 |
Work Progress Details | |||
---|---|---|---|
Physical progress | 25 % | ||
Current status | DPR approved by KIIFB on 09.11.2018 for an amount of Rs.89.774 Cr. GAD approved by Railways on 30.01.2023. Land taken possession started on 10.06.2024. 32/39 holdings handed over to RBDCK. TS will be convened after getting entire land from LAO. |