Projects

Atlantis ROB

Back

General Details
Administrative Sanction Order Number Dated Amount(crores)
GO(Rt)No.1324/2016/PWD 27.09.2016 50
District Ernakulam
LAC Ernakulam
Location
Project Details
Actual Start Date 15.02.2019
Project Management Consultant KITCO Ltd
Category Road Over Bridges
LC No 75A
Railway (km) 108/6-7
Length Including Approaches 523.92
Width of ROB 20.00
GAD Status Approved
No of Lanes 4
Financial Details
AS Amount(crores) 50
Funded By KIIFB
Project Outlay(crores) 89.774
Work Progress Details
Physical progress 25 %
Current status DPR approved by KIIFB on 09.11.2018 for an amount of Rs.89.774 Cr. GAD approved by Railways on 30.01.2023. LA Requisition submitted to DC on 15.02.2019. AS for LA obtained from Revenue Department as per GO Rt. 3387/2019/RD dt 06.11.2019.Land taken possession started on 10.06.2024. 22/34 holdings handed over to RBDCK. Joint inspection with KWA, KSEB & BSNL regarding utility shifting conducted on 16.10.2024, 26.11.2024 & 03.01.2025 respectively. TS will be convened after getting entire land from LAO.