General Details | |||
---|---|---|---|
Administrative Sanction | Order Number | Dated | Amount(crores) |
GO(Rt)No.1324/2016/PWD | 27.09.2016 | 50 | |
District | Ernakulam | ||
LAC | Ernakulam | ||
Location |
Project Details | |
---|---|
Actual Start Date | 15.02.2019 |
Project Management Consultant | KITCO Ltd |
Category | Road Over Bridges |
LC No | 75A |
Railway (km) | 108/6-7 |
Length Including Approaches | 523.92 |
Width of ROB | 20.00 |
GAD Status | Approved |
No of Lanes | 4 |
Financial Details | |
---|---|
AS Amount(crores) | 50 |
Funded By | KIIFB |
Project Outlay(crores) | 89.774 |
Work Progress Details | |||
---|---|---|---|
Physical progress | 25 % | ||
Current status | DPR approved by KIIFB on 09.11.2018 for an amount of Rs.89.774 Cr. GAD approved by Railways on 30.01.2023. LA Requisition submitted to DC on 15.02.2019. AS for LA obtained from Revenue Department as per GO Rt. 3387/2019/RD dt 06.11.2019.Land taken possession started on 10.06.2024. 22/34 holdings handed over to RBDCK. Joint inspection with KWA, KSEB & BSNL regarding utility shifting conducted on 16.10.2024, 26.11.2024 & 03.01.2025 respectively. TS will be convened after getting entire land from LAO. |