Current status |
DPR approved on 26.10.2018 for an amount of Rs.31.21 Cr. Land taking possession completed on 28.11.2022.
GAD approved by Railways on 09.11.2022.
The work was tendered on 06.09.2025, but only single bid received. Hence the work was retendered on 14.11.2024. Only one bidder, ULCCS has participated and the quoted amount is 24.34% higher than the estimate amount and 4.71% higher than LMR amount. RBDCK requested tender approval from the Secretary, PWD on 11.02.2025 and 10.04.2025.
Vide GO(Rt)No. 47/2025/FIN dated 11.04.2025 goverment issued orders for acceptance of bid where estimate is prepared SoR prior to the Introduction of DSoR 2021, but tender procedures are finalised after the applicability of DSoR 2021. Accordinly comparison has been based on DSR 2021 and negotiation letter sent to the bidder. The bidder has agreed to reduce the quoted amount DSR+10%, but not willing to reduce upto LMR amount. Hence requested tender approval from the Secretary, PWD on 11.06.2025. |