General Details | |||
---|---|---|---|
Administrative Sanction | Order Number | Dated | Amount(crores) |
GO (Rt) No. 942/2017/PWD | 10.07.2017 | 30 | |
District | Kottayam | ||
LAC | Kaduthuruthy |
Project Details | |
---|---|
Project Management Consultant | KITCO Ltd |
Category | Road Over Bridges |
LC No | 21 |
Railway (km) | 38/100-200 |
Length Including Approaches | 320.80 |
Width of ROB | 10.20 |
GAD Status | Not approved |
No of Lanes | 2 |
Financial Details | |
---|---|
AS Amount(crores) | 30 |
Funded By | KIIFB |
Project Outlay(crores) | 19.33 |
Work Progress Details | |||
---|---|---|---|
Physical progress | 2 % | ||
Current status | DPR approved by KIIFB on 28.06.2019 for an amount od Rs. 19.33 Cr. GAD approved on 14.11.2022. Revised LA requisition submitted to DC on 07.10.2022. Boundary stone planting completed and joint inspection with Revenue department is conducted on 12.01.2023. 11(1) notification published on 20.06.2024. Survey works in progress. Structural valuation completed and report given to PWD for vetting. |