General Details | |||
---|---|---|---|
Administrative Sanction | Order Number | Dated | Amount(crores) |
GO(Rt)No.718/2018/PWD | 19.04.2018 | 22.51 | |
District | Kasargod | ||
LAC | Kanhangad |
Project Details | |
---|---|
Actual Start Date | 11.08.2020 |
Project Management Consultant | ISA |
Category | Road Over Bridges |
LC No | 273 |
Railway (km) | 815/200-300 |
Length Including Approaches | 444.18 m |
Width of ROB | 10.20 |
GAD Status | Not approved |
No of Lanes | 2 |
Financial Details | |
---|---|
AS Amount(crores) | 22.51 |
Funded By | KIIFB |
Project Outlay(crores) | 34.71 |
Work Progress Details | |||
---|---|---|---|
Physical progress | 1 % | ||
Current status | DPR approved by KIIFB on 11.02.2020 for an amount of Rs.34.71 Cr. LA requisition submitted to the District Collector on 11.08.2020. GAD approved by Railways 19.12.2023. Boundary stone planting completed and Joint site inspection conducted on 28.02.2024. 4(1) notification published on 12.02.2025. SIA public hearing conducted on 03.04.2025 and report submitted to DC on 25.04.2025. Expert committee to be formed. |