Projects

Feroke ROB

Back View Gallery View Progress

General Details
Administrative Sanction Order Number Dated Amount(crores)
GO(Rt)No.454/2017/PWD 31.03.2017 19.01
Technical Sanction Order Number Dated Amount(crores)
RBDCK/T 177/TS-06/2020-21 18.02.2021 3.43
Revised Administrative Sanction Order Number Dated Amount(crores)
GO(Rt)No.1010/2021/PWD 19.11.2021 20.26
District Kozhikode
LAC Beypore
Location
Project Details
Actual Start Date 06.01.2022
Contractor(s) M/s PMR Construction Company
Project Management Consultant KITCO Ltd
Category Road Over Bridges
LC No Nil
Railway (km) 653/9 - 654/0
Length Including Approaches 545.52 m
Width of ROB 7.50m
GAD Status Railway Portion Completed
No of Lanes 2
Financial Details
AS Amount(crores) 19.01
Revised AS Amount(crores) 20.26
Funded By Govt Funded
Project Outlay(crores) 19.01
TS Amount(crores) 3.43
Tender Details
Tender No Dated Tender Amount(crores)
RBDCK ROB/T77/Vol III/ 114/2021 04.06.2021 3.1
Agreement Details
Agreement No Agreement Date Agreed Amount(crores) Site Handover Date Period of Completion Actual Date of Completion
RBDCK/T 77/48/2021 27.12.2021 3.59 06.01.2022 9 months 05.10.2022
Work Progress Details
Physical progress 98 %
Current status Opened to traffic on 14.11.2023. As the amount for the Construction of approach portion of the ROB is increasing from Rs. 20.26 Cr to Rs 22.41 Cr, request for Revised AS was submitted to Secretary, PWD on 18.10.2022. Secretary PWD enquired some clarifications and reply for the same was submitted on 30.01.2023, 26.07.2023 & 27.09.2023. Waiting for the Revised AS from GoK.
View Gallery View Progress