Current status |
Administrative Sanction was accorded on 18.08.2014 for an amount of Rs.25.17 Cr. The work was included in the Railway work plan 2006-07 and due to delay in Land acquisition the work was deleted from work paln. LA was completed on 30.06.2022.
Government of Kerala requested Railways to re-include this ROB in Pink Book of Railway Work Programme for the year 2022-23. LA completed on 02/08/2022. Later RBDCK requested for revised AS.
GoK then informed that the request for revised AS can be considered only after the re-inclusion of this ROB in Railway Pink Book. Letter to DRM to recalculate TVU and include in railway work plan send on 20.07.2023_informed to Minister for Road Transport. During the review meeting conducted by DRM on 21.08.23, RBDCK requested the same, letter to PCE from DRM send on 25.08.2023. Reminder letter sent to DRM on 05/06/2024. The same was intimated to PWD Secretary on 19/06/2024 for further necessary actions. Vide letter dated 23.08.2024, PWD secretary has requested DRM regarding resurvey at LC. |