Current status |
DPR approved by KIIFB on 11.02.2020 for an amount of Rs.10.61 Cr (for river bridge and LA of ROB only). LA Completed.
Design and drawings approved by IIT and the same with revised estimate was submitted to TS committe on 27/12/2023. Estimate was returned with comments on 29.01.2024 and the same resubmitted on 05.02.2024. TS for construction issued on 08.02.2024 and submitted to KIIFB for approval. Revised TS approved by KIIFB on 25.11.2024, work was tendered on 04.12.2024.
After several revisions Railways directed to submit the GAD to CBE Chennai as this is a deposit work. Also, Railways directed to submit the GAD along with the joint feasibility report. Joint Feasibility report was submitted to ADEN, Palakkad for signature on 06.04.2022. Revised GAD was submitted to Railways on 13.06.2022.
Meanwhile on 17.11.2023, KIIFB instructed to wait until the TVU comes 1 lakhs. |