| General Details | |||
|---|---|---|---|
| Administrative Sanction | Order Number | Dated | Amount(crores) |
| GO(Rt)No.718/2018/PWD | 19.04.2018 | 22.51 | |
| District | Kozhikode | ||
| LAC | Koyilandy | ||
| Project Details | |
|---|---|
| Actual Start Date | 19.04.2018 |
| Project Management Consultant | ISA |
| Category | Road Over Bridges |
| LC No | 205 |
| Railway (km) | 691/400-500 |
| Length Including Approaches | 391.28 m |
| Width of ROB | 10.20 m |
| GAD Status | Not Approved |
| No of Lanes | 2 |
| Financial Details | |
|---|---|
| AS Amount(crores) | 22.51 |
| Funded By | KIIFB |
| Project Outlay(crores) | 36.12 |
| Work Progress Details | |||
|---|---|---|---|
| Physical progress | 74 % | ||
| Current status | The DPR was approved by KIIFB on 07.02.2020 for an amount of Rs. 36.12 crore. LA delayed due to Semi High Speed Rail Project of KRDCL and GAD approval. In the meeting conducted with the Kozhikode District Collector on 24.05.2025, it was decided to construct the Nelliyady Kadavu ROB and provide connectivity to Muchukunnu through a service road. | ||