Projects

Kozhikkal ROB

Back

General Details
Administrative Sanction Order Number Dated Amount(crores)
GO(Rt)No.718/2018/PWD 19.04.2018 22.51
District Kannur
LAC Thalassery
Project Details
Actual Start Date 19.04.2018
Project Management Consultant ISA
Category Road Over Bridges
LC No 227
Railway (km) 731/100-200
Length Including Approaches 541.00 m
Width of ROB 10.20 m
GAD Status Not Approved
No of Lanes 2
Financial Details
AS Amount(crores) 22.51
Funded By KIIFB
Project Outlay(crores) 46.57
Work Progress Details
Physical progress 74 %
Current status DPR approved by KIIFB on 07.02.2020 for an amount of Rs.46.57 Cr. LA to be taken up after getting approval of GAD from railways. At the same time, Railways constructed an underpass at the same location and the Railway gate is already closed. Pointing out that, Hon. MLA recommended holding the project until necessary decision is taken. Hon. MLA directed to cancel the project on 22.08.2022 at Thalassery CMT meeting. Informed the same to GoK on 27.01.2023. On 21.02.2023 KIIFB also recommended GoK to exclude the project from KIIFB funding. Accordingly on 20.04.2023 GoK exclude the work from the GO dated 19.04.2018.