General Details | |||
---|---|---|---|
Administrative Sanction | Order Number | Dated | Amount(crores) |
GO(Rt)No.718/2018/PWD | 19.04.2018 | 22.51 | |
District | Kasargod | ||
LAC | Thrikaripur | ||
Location |
Project Details | |
---|---|
Actual Start Date | 19.04.2018 |
Project Management Consultant | ISA |
Category | Road Over Bridges |
LC No | 267 |
Railway (km) | 795/500-600 |
Length Including Approaches | 521 m |
Width of ROB | 10.2 m |
GAD Status | Not Approved |
No of Lanes | 2 |
Financial Details | |
---|---|
AS Amount(crores) | 22.51 |
Funded By | KIIFB |
Project Outlay(crores) | 32.24 |
Work Progress Details | |||
---|---|---|---|
Physical progress | 75 % | ||
Current status | DPR approved by KIIFB on 10.02.2020 for an amount of Rs.32.24 Cr. GAD approved on 28.11.2024. LA plan prepared. Requisition for acquisition submitted to District collector on 30.01.2025. Revenue AS obtained on 05.04.2025. 6(1) notification pending. |