Projects

Edachakkai Nadakkavu ROB

Back

General Details
Administrative Sanction Order Number Dated Amount(crores)
GO(Rt)No.718/2018/PWD 19.04.2018 22.51
District Kasargod
LAC Thrikaripur
Location
Project Details
Actual Start Date 19.04.2018
Project Management Consultant ISA
Category Road Over Bridges
LC No 267
Railway (km) 795/500-600
Length Including Approaches 521 m
Width of ROB 10.2 m
GAD Status Not Approved
No of Lanes 2
Financial Details
AS Amount(crores) 22.51
Funded By KIIFB
Project Outlay(crores) 32.24
Work Progress Details
Physical progress 75 %
Current status DPR approved by KIIFB on 10.02.2020 for an amount of Rs.32.24 Cr. LA to be taken up after getting approval of GAD from railways. Project was pending due to Semi High Speed Rail project of KRDCL. On 06.12.2022, KRDCL had informed to go ahead with the construction of ROBs without considering the silver line alignment and RBDCK intimated the same to Railways on 08.12.2022. Railways directed to submit revised GAD for all ROBs long pending due to Silver line vide letter dated 14.03.2023. Appointed the Consultancy M/s JH for the revision of GAD and alignment on 17.03.2023. Revision of GAD under process. LUS inspection conducted on 22.06.2023. Revised GAD with LUS report submitted to Railways on 10.08.2023. Reminder letter submitted on 27.10.2023.