Current status |
DPR approved by KIIFB on 10.02.2020 for an amount of Rs.40.64 Cr. LA plan under preparation. The requisition will be submitted to District Collector after the approval of GAD from Railways.
A joint site inspection was carried out with NHAI and ULCCS representative on 18.10.2021 at Hosangadi. On 20.10.2021 NHAI sent a letter and requested to modify the alignment. Accordingly, RBDCK sent a letter to M/s ISA to revise the drawing of Hosangadi ROB on 05.11.2021. But, M/s ISA informed that they required both vertical and horizontal alignments of NH project under execution to suit the profile. Sent a request to NHAI for the same on 31.12.2021. According to that NHAI conducted an online meeting with RBDCK, ISA and ULCCS representative on 15.01.2022 and informed that the plan and profile of NH at Hosangadi portion will be finalized and submitted soon. Reminder letter send to NHAI on 14.07.2022 and 18.11.2022. Sr. Project Manager ULCCS submitted the plan and profile of NH 66 at Km 24+188 (Hosangadi) on 27.11.2022. The same was forwarded to consultant ISA and directed to revise the alignment of ROB on 28.12.2022.
Meanwhile, as per request of M/s ISA we had foreclosed the contract. Now appointed M/s JH consultants for the preparation of GAD. On 07.11.2023 joint site inspection with ULCCS surveyor was conducted to get coordinates for superimposing both alignments for revising ROB alignment with respect to NHAI alignment. On 16.11.2023 ULCCS submitted the coordinates. Revised GAD submitted to Railways on 01.02.2024. |