Temple Road ROB

Back

General Details
Administrative Sanction Order Number Dated Amount(crores)
GO(Rt)No.718/2018/PWD 19.04.2018 22.51
District Kozhikode
LAC Kozhikode North
Location
Project Details
Actual Start Date 19.04.2018
Project Management Consultant ISA
Category Road Over Bridges
LC No 189
Railway (km) 669/700-800
Length Including Approaches 497.39m
Width of ROB 10.20 m
GAD Status Not Approved
No of Lanes 2
Financial Details
AS Amount(crores) 22.51
Funded By KIIFB
Project Outlay(crores) 36.84
Work Progress Details
Physical progress 75 %
Current status DPR approved by KIIFB on 09.08.2020 for an amount of Rs.36.84 Cr. LA to be taken up after getting approval of GAD from railways. Project was pending due to Semi High Speed Rail project of KRDCL. Railways directed to submit revised GAD for all ROBs long pending due to Silver line vide letter dated 14.03.2023. LUS inspection conducted on 04.07.2023 and report received. . The Railway GAD was on hold due to SV loading issues. In the meeting convened on 08.10.2024, CAO/RSP had instructed some modifications and instructed to resubmit the GADs. Revised GAD submitted on 06.01.2025. As requested by Railways, revised GAD submitted to Railways on 04.03.2025. In the meeting conducted with the Kozhikode District Collector on 24.05.2025, it was decided to construct the Chungam Gate ROB and provide connection to Temple Gate via a service road.