Projects

Temple Road ROB

Back

General Details
Administrative Sanction Order Number Dated Amount(crores)
GO(Rt)No.718/2018/PWD 19.04.2018 22.51
District Kozhikode
LAC Kozhikode North
Location
Project Details
Actual Start Date 19.04.2018
Project Management Consultant ISA
Category Road Over Bridges
LC No 189
Railway (km) 669/700-800
Length Including Approaches 497.39m
Width of ROB 10.20 m
GAD Status Not Approved
No of Lanes 2
Financial Details
AS Amount(crores) 22.51
Funded By KIIFB
Project Outlay(crores) 36.84
Work Progress Details
Physical progress 75 %
Current status The DPR was approved by KIIFB on 09.08.2020 for an amount of Rs. 36.84 crore. LA delayed due to Semi High Speed Rail Project of KRDCL and GAD approval. In the meeting convened with the Kozhikode District Collector and Railways on 24.05.2025, it was decided to construct the Chungam Gate ROB and provide connection to Temple Gate via a service road.