Projects

Ollal ROB

Back

General Details
Administrative Sanction Order Number Dated Amount(crores)
GO(Rt)No.771/2018/PWD 27.04.2018 22.66
District Kollam
LAC Chathannoor
Location
Project Details
Actual Start Date 27.04.2018
Project Management Consultant ISA
Category Road Over Bridges
LC No 554
Railway (km) 168/400-500
Length Including Approaches 513.04 m
Width of ROB 10.20 m
GAD Status Not Approved
No of Lanes 2
Financial Details
AS Amount(crores) 22.66
Funded By KIIFB
Project Outlay(crores) 36.75
Work Progress Details
Physical progress 74 %
Current status DPR approved on 06.08.2020 for an amount of Rs.36.75 Cr. LA requisition will be submitted after the approval of GAD from Railways. On submission of GAD, Railways informed that the work was deleted from Railway work plan. Hence requested Railways to include the work in Railway work plan on 24.08.2021. On 11.08.2023, Railways informed that the work is included in the railway work programe 2023-24. Joint Inspection for LUS conducted on 24.11.2023. GAD Submitted to Railways on 30.12.2023. Railways returned for modification on 23/02/2024. The Railways had informed that all the future ROB superstructures are to be designed for Special Vehicle Loading. After several revisions, Revised GAD submitted on 06.01.2025. Railway Returned the GAD for correction on 11.06.2025. Revision of drawing in progress and will be submitted to Railways on 25.06.2025.